Website project timeline: how long a B2B website really takes

Our plan, and what actually happened on four client projects. Some ran long. We show those too.

In short

The short answer

Updated 17 Oct 2026

A full website usually takes 6 weeks with us: copy and design in weeks 1 to 3, build in weeks 3 to 5, checks and launch in week 6. A landing page takes 2 to 3 weeks. The written scope comes within 3 business days of the first call. Real projects vary. On four recent client projects, the dates on our Contra project pages run from under a week to more than 20 weeks.

Our plan, week by week

The same plan as on our process page.

WhenStepWhat happensWhat you get
KickoffCall and scopeA 30-minute call with Erfan. We give you the price and the date before we design anything.A written scope, price and launch date, and the contract, within 3 business days.
Weeks 1 to 3Messaging and designWe write the copy first, then design every page. You see the work every week.Your story, page plan and headlines, then every page for desktop and phone.
Weeks 3 to 5DevelopmentBuilt so your team can edit it without a developer.CMS, forms, analytics and the SEO basics.
Week 6Check and launchLive on the date in your contract. Old links point to the new pages.Every page checked on phones and laptops.
After launchHandoverEverything is handed over to you.A recorded walkthrough, every account handed over and 30 days of free fixes.

Real projects, real dates

Start and end dates as our Contra project pages show them. Three of the four ran past our 6-week plan, and two ran far past it. The pages show when each project started and ended, not why, so we don’t guess here.

ProjectWhat we didPlatformDatesStart to end
FronterraDesigned and builtFramer22 – 27 Jan 20266 days
Machine Football AIDesigned and builtFramer21 Jan – 19 Mar 20268 weeks and 2 days
NOCAP SportsBuilt, from their designWebflow19 Oct 2025 – 13 Jan 202612 weeks and 3 days
ComtelDesigned and builtWebflow24 Oct 2025 – 16 Mar 202620 weeks and 4 days

Source: Pentaclay project pages on Contra, read 17 Oct 2026.

What other studios state

Timelines as each studio states them on its own site.

WhoTypeStated timeline
GoodspeedFramer studioAbout three weeks to go live
Allsite StudioFramer studioThree to five weeks
AmplyB2B web agency4 to 6 weeks
RefokusWebflow agency“Most projects take around 8 to 14 weeks.”
KOTAB2B agency12 to 14 weeks

Source: Each studio’s own website, as recorded in Pentaclay’s agency research, 9 and 10 Oct 2026.

What changes a timeline

Messaging and copywriting

We write the copy first, and you approve it before we design. The sooner the copy is agreed, the sooner design starts.

Your product screens

If the real screens don’t exist yet, we use product frames, diagrams or a short recording, so the site doesn’t wait for them.

How many pages

A landing page takes 2 to 3 weeks instead of 6. If one landing page gets you there, we scope that instead.

An existing site

A redesign or a move adds a URL list and a redirect map before launch.

A date in the contract

Tell us the date on the call. If we can’t hit it, we say so. The date we agree goes into the contract.

Plan backwards

Pick your launch date. Count back 6 weeks, then a few days more for the written scope. That’s when to book the call.

When we’re not the right fit

If you need the site live in under 3 weeks, we’re not the right team. A website template is faster.

Timeline questions

Can’t find your answer?

Book a call and let’s talk.

Book a call

Or email us at contact@pentaclay.com

How long does a website project take?

With us, usually 6 weeks for a full website and 2 to 3 weeks for a landing page. The studios we checked state anywhere from about three weeks to 14 weeks.

What are the stages of a website project?

Ours has five: call and scope, messaging and design in weeks 1 to 3, development in weeks 3 to 5, check and launch in week 6, then handover.

Why did some of your projects take longer than 6 weeks?

Our Contra pages show three of four recent projects ran past 6 weeks, and we show them as they are. On the call, tell us your date. If we can’t hit it, we say so, and the date we agree goes into the contract.

Can a website be done in under 3 weeks?

Not with us. If you need a site in under 3 weeks, a website template is the faster route. We publish more than 100 of them.

When do we get the scope and price?

Within 3 business days of the call, in writing, with the launch date.

Your business grew up. Your website should too

If customers need a demo just to understand what you sell, your website isn’t doing its job.

  • We sign an NDA on request.
  • You own the site, the code and every account once it’s paid.
  • Your first call is with Erfan, the founder.

Kazi Mohammed ErfanFounder

What do you need?
Budget

Don’t want to fill in the form? Book a call directly

Not sure? Ask AI about Pentaclay

Pentaclay, in short

Pentaclay is a B2B website design agency for AI companies that sell to enterprises. We write, design and build marketing websites in Framer, Webflow and Next.js, and stay to help after launch. Pentaclay LLC is registered in New Mexico, USA; our team works from Dhaka, Bangladesh, with calls until 12:30pm US Eastern. Founded in 2023 by Kazi Mohammed Erfan, who brings 12 years of design experience.